Board of Public Works

2008 Street and Sidewalk Improvement Program
Tuesday, March 11, 2008
Council Chambers
3:00 p.m.

The Board of Public Works was called to order by Mayor Claude Lois at 3:02 p.m. with the following in attendance: Alderman Robert Miller, Attorney Tom Kircher, City Administrator Mr. Kevin Lahner, Utility Manager Ms. Connie Wilson, Public Works Supervisor Mr. Larry Gobel, Engineering Technician Ms. Judy Gerulat, Mr. Mike Timmers and Mr. Tom Foht of Kapur Engineering.

A motion was made by Alderman Miller to accept the September 13, 2007 Minutes. Attorney Kircher seconded the motion and with all in favor the motion carried.

The following bids were presented:

A.W. Oakes

Reesman's Excavating

Wanasek Corporation

Willkom Excavating

Total Base Bid

$914,454.85

$800,713.50

$839,761.40

$967,273.27

Alt No. 1A-Riverwalk Shot-blast/Mill

$16,298.00

$10,678.00

$6,744.00

$5,445.78

Alt. No. 1B-Riverwalk Remove & Replace

$22,262.00

$30,696.00

$29,821.80

$20,092.20

Receipt of Addendum No. 1
Bid Guaranty

A motion was made by Alderman Miller to refer the bids to engineering staff for recommendation. Attorney Kircher seconded the motion and all were in favor.

A motion was made by Alderman Miller to adjourn the meeting. Attorney Kircher seconded the motion and with all in favor, the meeting adjourned at 3:08 p.m.

Respectfully submitted,

Beverly R. Gill
City Clerk
City of Burlington
Racine and Walworth County

 