HISTORIC PRESERVATION COMMISSION
MEETING MINUTES
COMMON COUNCIL CHAMBERS
July 27, 2006
Chairman Tom Stelling called the meeting to order at
6:30 p.m.
Roll Call: Present: Commissioners Bob
Henney, Kent Strong , Steve Whittow and Chairman Tom
Stelling. Absent and excused: Joe Busch, Susan Kott and
Pat Scherrer, Building Inspector for City of Burlington.
Also absent: Judy Stone. Also present: Francesca Bumpurs
of RCEDC.
Citizens Comments: None
Approval of March 23, 2006 Meeting Minutes:
Chairman Stelling stated the four HPC Commissioners who
attended the March 23, 2006 meeting were not all present
and therefore the Minutes would again be tabled.
Approval of June 22, 2006 Meeting Minutes:
Chairman Stelling entertained a motion for approval of
the June 22, 2006 Minutes. Commissioner Strong motioned,
seconded by Commissioner Whittow. All voted aye, motion
carried.
Certificate of Appropriateness Application
Dale Bruesewitz, 140 W. Chestnut Street, Burlington,
WI 53105
Mr. Bruesewitz was present to present his Certificate
of Appropriateness Application which proposed painting
the existing metal awning in addition to the trim work.
Colors presented were Roycroft Copper Red with three
stripes of Peace Yellow at each end of the awning. In
addition, the applicant proposed painting all wood trim
around and below the windows in Peace Yellow as
indicated in drawing provided.
The Commissioners discussed the non conforming metal
awning and felt the color choice for striping may need
enhancement. After some discussion, the Commissioners
discussed doing a Response Team Visit to determine if
colors were appropriate once the awning had been cleaned
and primed.
Chairman Stelling entertained a motion to recommend
approval of the Certificate of Appropriateness
Application to Dale Bruesewitz for his project at 140 W.
Chestnut Street to allow cleaning, priming and a sample
paint color on the awning to allow a Response Team Visit
to determine appropriate color details of the metal
awning and wood trim for final recommendation. Date of
Response Team Visit to be on August 7th or 8th,
with Mr. Bruesewitz contacting either Chairman Stelling
or Francesca Bumpurs to determine exact date and time.
Commissioner Strong motioned for approval, seconded by
Commissioner Henney. There was no further discussion,
all voted aye and motion carried.
Mr. Bruesewitz stated he may also be interested in
doing additional work on the façade. Chairman Stelling
indicated that additional work could be added, if
approved, by amending his Certificate of Appropriateness
Application once it is approved, or by submitting a new
application.
Discussion of Current Projects and Response Team
Updates.
|
Applicant/Business |
Address |
Project |
Date Approved |
|
Rizzo & Diersen
Nothing new at this
time |
115 Commerce St. &
549 Milwaukee Ave. |
Various façade
improvements
Signage
Lighting |
9/23/04 & 2/24/05
11/17/05
12/22/05 |
|
Neil DeMant/Kerkman’s
Split Ends, LLC
Nothing new at this
time |
316 N. Pine St. |
Bulkhead windows to
resemble existing with four (4) separate pieces
of glass and transom to resemble 336 N. Pine
Street;
Removal of tile bulkheads and replacement with
smooth textured Cement Coat Plus™, color
off-white. |
8/25/05 |
Simon Malek
Francesca Bumpurs to contact applicant |
316-336 N. Pine St |
Tuckpointing, brick
repair, etc. |
10/27/05 |
Constance
Stellmacher Law Offices
·140 Rear windows still an issue
Lien Waivers Received |
484 N. Pine St. |
Scrape rear
exterior exposed wood and paint to match
existing color (Chick Pea #59); wrought iron
window openings to be painted black. |
10/27/05 |
Dave Berlin
Francesca Bumpurs to check status |
120 West Chestnut
St. |
Various façade
improvements
*completed elevation with colors noted & partial
floorplan to be submitted to Building Inspector
for review of Code conformity. |
3/23/06 |
Johnson Bank
Completed, Remove from List |
101-105 West
Chestnut St. |
Awning |
6/22/06 |
Review of §315-139, Certificate of Appropriateness
Chairman Stelling stated that the Certificate of
Appropriateness Application should be reviewed by the
Commissioners to determine if all required information
is listed on the application. Judith Schulz stated that
she felt informing applicants that historic pictures be
provided to the HPC was an important factor.
Certificate of Appropriateness Packets in addition to
Sign Permit Applications are distributed either through
Pat Scherrer at City Hall or Francesca Bumpurs of RCEDC.
Chairman Stelling stated they would verify with Pat
Scherrer, Building Inspector that all information is
provided when applicants request Appropriateness
Applications.
Discussion on possible new definitions/ordinances for
repaint, touch-ups, color change and seasonal timing of
requests.
Francesca Bumpurs compiled information from various
historic communities for comparison use regarding
definitions and ordinances for repaint, touch-up, color
change and season timing of requests. Chairman Stelling
stated he would prefer all Commissioners be present for
discussion and therefore discussion would be at a later
date when the majority of Commissioners were in
attendance.
Review of Grant Funding Status.
| Grant Fund #2: |
$50,000.00 |
| Total Approved for Funding: |
$50,000.00 |
| Total Disbursed: |
$28,598.19 |
| Funds not yet disbursed: |
$21,140.81 |
| Amount Remaining: |
$0.00 |
Francesca Bumpurs of RCEDC stated it would be some
time before information regarding interest earned would
be available from City Hall.
Questions and Comments concerning potential/future
projects
None
There being no further items for discussion, Chairman
Stelling entertained a motion for adjournment.
Commissioner Henney motioned, seconded by Commissioner
Strong. Chairman Stelling adjourned the meeting at 7:00
p.m.
Minutes respectfully submitted by:
Deb Rintamaki
Department of Public Works
|